PA 153 Clearfield Creek Bridge, Clearfield Co.

FRANCIS J. PALO, INC. was awarded a contract on October 26, 2006, with the Commonwealth of Pennsylvania, Department of Transportation for the construction of a certain section of STATE HIGHWAY in CLEARFIELD COUNTY, LAWRENCE and BOGGS TOWNSHIPS, STATE ROUTE 0153, SECTION A02. This project was located on SR 0153 approximately 2.2 miles north of its intersection with SR 2024 and continuing northward for approximately 1,200 feet, located between Segment 0300 Offset 1602 and Segment 0310 Offset 1044. Palo, Inc. removed the existing Five-Span Prestressed Concrete I-Beam Bridge and replaced it with a Three-Span Prestressed Concrete I-Beam Bridge (approximate length of 344 feet). The project started on March 12, 2007 and was completed on October 12, 2007.

 

 